Chelsea & Westminster Health Centre SW10

Case Study: Fast-Track AHU Base & Enclosure Structural Engineering

Project: Lower Ground Floor Treatment Room AHU Base & Acoustic Enclosure

Location: Chelsea and Westminster Hospital, London

Client: NHS Foundation Trust

Role: Structural Engineers

Executive Summary

Appointed mid-construction, our structural engineering team designed the reinforced concrete base and protective enclosure for a new Air Handling Unit (AHU) serving the hospital’s lower ground floor treatment room. Facing a non-negotiable plant delivery date, we executed rapid geotechnical investigations and coordinated closely across multidisciplinary teams to issue full construction drawings ahead of plant arrival.

Project Context & Structural Challenge

With contractor works already underway on site, the installation faced a strict constraint: a fixed manufacturer delivery date for the AHU. Delaying the foundation or enclosure design would have disrupted hospital operations and caused costly project delays.

Key engineering challenges included:

  • Compressed Schedule: Completing structural calculations and construction drawings on an expedited turnaround while site work was actively progressing.
  • Subsoil Verification: Rapidly determining the subsoil’s safe bearing capacity beneath the proposed footprint.
  • Complex Logistics: Managing site access and ground investigation equipment through an active, sensitive hospital environment.

Technical Solutions & Stakeholder Coordination

Fast-Turnaround Ground Investigation

We promptly commissioned and managed a targeted site investigation to establish subsoil load-bearing parameters and settlement limits for the heavy mechanical plant without interrupting daily hospital activities.

Multi-Disciplinary Collaboration

Meeting the tight program required rapid alignment across key project stakeholders:

  • NHS Foundation Trust & Estate Facilities Manager: Coordinated safe access routes, work permits, and logistics within live hospital zones.
  • M&E Engineers: Verified plant operating loads, weight distributions, duct penetrations, and vibration isolation needs for the AHU and acoustic enclosure.
  • Client QS & Main Contractor: Aligned structural details with budget constraints and facilitated immediate on-site execution upon drawing release.

Foundation & Enclosure Design

  • Engineered a reinforced concrete slab base designed to distribute static loads and dampen dynamic equipment vibrations.
  • Developed structural framing for the acoustic enclosure to withstand wind and maintenance loads while enabling rapid assembly.

Results & Delivery

  • On-Time Package: Issued all structural design packages and detailed construction drawings within the client’s tight timeframes.
  • Minimal Disruption: Carried out site testing and access setup without disturbing patient care or clinical workflows.
  • Seamless Installation: Completed base construction and enclosure framing on schedule, allowing immediate placement of the AHU upon site delivery.